2020-08-19 Integration Meeting Minutes
Date & Time
August, 19th, 2020; 9pm PST
Agenda
Release
Infra
Docs
Misc
Minutes
Release:
Aluminium . Aug 3, 2020 is Aluminium code freeze
last 6 autorelease has all failed
acutally, the last autorelease passed the build, but some signing cert failure makes the jenkins job mark as aborted
@Thanh Ha will open a ticket with LF to get the signing cert fixed
2 blocker bugs
NETCONF-716 will be lead by @JamO Luhrsen
BGPCEP-919 needs an update from @Venkatrangan Govindarajan
2 bugs on INTTEST project that we can hopefully fix before the release
Sodium SR4 is hopefully on track for the end of August Aug 21, 2020 for SR4 release SR4 checklist
looks like the last 3 failing jobs might be intermittent failures and not regressions. @JamO Luhrsenwill double check today and if all is well, we can release SR4 this week
Silicon release started
the vote for the schedule has passed
Magnesium SR2 is out and docs are updated. SR3 will be next and the final Mg release in mid-November
Infra:
Last week our CSIT jobs were failing because of some missing certificate. That was fixed last week, but now we realize that
our autorelease jobs are failing for a similar issue. A new ticket is now open.our tooling was not notifying us that the jobs were failing because the real work (the build) was just fine. This was
yet another infra issue.
Docs:
some recent docs patches were abandoned, but we might restore those and see if we can finish
Misc:
netvirt jobs have some new python dependency failures that @Srinivas Rachakondais working on. but stacking is failing