2020-07-29 Integration Meeting Minutes
Date & Time
July, 29th, 2020; 9pm PST
Agenda
Release
Infra
Docs
Misc
Minutes
Release:
Mg-SR2
release is delayed by aprox two week now... original date was Jul 20, 2020 but delayed to Aug 3, 2020
two CSIT issues marked as blocker. one might not be but need community input on that. the other is still being debugged
Aluminium . Aug 3, 2020 is Aluminium code freeze (next week)
3 out of last 4 autorelease has passed
Sodium SR4 is hopefully on track for the end of August Aug 24, 2020 for SR4 code freeze
latest MRI bump is now finished
Infra:
no supercomitter permissions should be there at this time. all MRI bumps for all branches are done
@Anil Shashikumar Belur wondering why this job is failing.
this is an LF job to verify if images exist or not and seems some image is not there
the nexus URL in the quagga job does not work. Anil planning to help Srinivas via irc/email
Docs:
The netconf user guide is being broken up in to modules
Misc:
The team is wondering if we can get weekly reports (instead of monthly) for infra job costs or if we can
drill down in to specific projects to see what jobs may be the heavy hitters.
Action Items
@Daniel De La Rosa to send an email reminder that Aluminium code freeze is next week.
@Anil Shashikumar Belur to check that all super committer permissions are revoked