Release Schedule for Potassium

More details at https://docs.opendaylight.org/en/stable-silicon/release-process/release-schedule.html

Event / Timeline

Potassium

Argon

Chlorine

Event / Timeline

Potassium

Argon

Chlorine

Start of the Release

Mar 16, 2023 

Sep 22, 2022 

Mar 17, 2022 

Initial Checkpoint

Mar 30, 2023 

Oct 6, 2022 

Mar 31, 2022 

Release integrated deadline

Apr 20, 2023 

Oct 20, 2022  

Apr 14, 2022 

Version Bump

Apr 21, 2023 

Oct 21, 2022 

Apr 15, 2022 

Version bump checkpoint

Apr 27, 2023 

Nov 3, 2022

Apr 29, 2022 

CSIT checkpoint

May 11, 2023 

Nov 17, 2022 

May 13, 2022 

Middle Checkpoint

Jul 6, 2023 

Jan 12, 2023 

Jul 7, 2022 

Code Freeze/Branch Cutting

Aug 3, 2023 

Feb 9, 2023 

Aug 4, 2022 

Final Checkpoint



Aug 17, 2023 

Feb 23, 2023 

Aug 19, 2022 

Formal Release

(6 months after Start Date)

Sep 21, 2023 

Mar 16, 2023 

Sep 19, 2022 

1.5 month after Formal Release

Oct 26, 2023 

Apr 27, 2023 

Oct 24, 2022 

4.5 months after Formal Release

Jan 25, 2024 

Jul 27, 2023 

Jan 23, 2023 

7.5 months after Formal Release

May 9, 2024 

Oct 26, 2023 

May 8, 2023 









12 months after Formal Release

Sep 19, 2024 

Mar 21, 2024 

Sep 19, 2023