Event / Timeline | Phosphorus | Sulfur | Chlorine |
---|---|---|---|
Start of the Release | Mar 17, 2021 | Sep 23, 2021 | Mar 17, 2022 |
Mar 31, 2021 | Oct 7, 2021 | Mar 31, 2022 | |
Release integrated deadline | Apr 15, 2021 | Oct 21, 2021 | Apr 14, 2022 |
Version Bump | Apr 16, 2021 | Oct 22, 2021 | Apr 15, 2022 |
Version bump checkpoint | Apr 29, 2021 | Nov 4, 2021 | Apr 29, 2022 |
CSIT checkpoint | May 13, 2021 | Nov 18, 2021 | May 13, 2022 |
Jul 8, 2021 | Jan 13, 2022 | Jul 7, 2022 | |
Code Freeze/Branch Cutting | Aug 5, 2021 | Feb 10, 2022 | Aug 4, 2022 |
| Aug 19, 2021 | Feb 24, 2022 | Aug 19, 2022 |
Formal Release (6 months after Start Date) | Sep 16, 2021 | Mar 17, 2022 | Sep 19, 2022 |
1.5 month after Formal Release | Oct 28, 2021 | Apr 28, 2022 | Oct 24, 2022 |
4.5 months after Formal Release | Jan 27, 2022 | Jul 28, 2022 | Jan 23, 2023 |
7.5 months after Formal Release | May 12, 2022 | Oct 28, 2022 | May 8, 2023 |
|
|
|
|
12 months after Formal Release | Sep 15, 2022 | Mar 16, 2023 | Sep 19, 2023 |