Release Schedule for Chlorine

More details at https://docs.opendaylight.org/en/stable-silicon/release-process/release-schedule.html

Event / Timeline

Phosphorus

Sulfur

Chlorine

Event / Timeline

Phosphorus

Sulfur

Chlorine

Start of the Release

Mar 17, 2021 

Sep 23, 2021 

Mar 17, 2022 

Initial Checkpoint

Mar 31, 2021 

Oct 7, 2021 

Mar 31, 2022 

Release integrated deadline

Apr 15, 2021 

Oct 21, 2021 

Apr 14, 2022 

Version Bump

Apr 16, 2021 

Oct 22, 2021 

Apr 15, 2022 

Version bump checkpoint

Apr 29, 2021 

Nov 4, 2021 

Apr 29, 2022 

CSIT checkpoint

May 13, 2021 

Nov 18, 2021 

May 13, 2022 

Middle Checkpoint

Jul 8, 2021 

Jan 13, 2022 

Jul 7, 2022 

Code Freeze/Branch Cutting

Aug 5, 2021 

Feb 10, 2022 

Aug 4, 2022 

Final Checkpoint

 

Aug 19, 2021 

Feb 24, 2022 

Aug 19, 2022 

Formal Release

(6 months after Start Date)

Sep 16, 2021 

Mar 17, 2022 

Sep 19, 2022 

1.5 month after Formal Release

Oct 28, 2021 

Apr 28, 2022 

Oct 24, 2022 

4.5 months after Formal Release

Jan 27, 2022 

Jul 28, 2022 

Jan 23, 2023 

7.5 months after Formal Release

May 12, 2022 

Oct 28, 2022 

May 8, 2023 

 

 

 

 

12 months after Formal Release

Sep 15, 2022 

Mar 16, 2023 

Sep 19, 2023