Milestone | Offset 1 Date | Deliverables |
---|
M1 | 10/27/2016 | Name | Status | Description |
---|
Intent to participate | Done | Intent to participate in Carbon Simultaneous Release | Project/Test Lead elected | Done | SXP Project/Test Lead election | Candidate Release Plan | Done | Candidate Release Plan |
|
M2 | 12/1/2016 | Name | Status | Description |
---|
Release Plan | Done | Final Release Plan | Project Checklist | Done | Project Checklist completed | OpenDaylight CI | Done | OpenDaylight CI infrastructure usage for system test |
|
M3 | 1/19/2017 | Name | Status | Description |
---|
Functionality Freeze | Done | Final list of externally consumable APIs defined and documented | Karaf Features defined | Done | Karaf Features defined | Documentation Started | Done | Identified the kinds of documentation to be provided, created AsciiDoc files for them with outlines, and committed those files in an appropriate location | Integration & System Test | Done | Simple system test on a karaf distribution with the project's recommended features installed |
|
M4 | 2/16/2017 | Name | Status | Description |
---|
API Freeze | Done | Final defined API | Documentation | Done | Documentation draft proposal | Maven Central Requirements | No | Accomplished/Not Accomplished | Integration & System Test | Done | Participating projects must run a simple system test on a karaf distribution with the project's recommended features installed on Code Merge | Sxp Cluster master instance routing | Done | Sxp Cluster master instance routing | Inbound Messages Buffering | Done | Incoming Update Messages buffering | Multi Async Transactions for SXP-Node | Done | DatastoreAccess migration |
|
M5 | 3/16/2017 | Name | Status | Description |
---|
Code Freeze | Done | Bug fixes only from here | Stability branch | Done | Stability branch stable/carbon, must be cut and local project versions bumped on master to avoid overwriting carbon SNAPSHOTS | String Freeze | Done | All externally visible strings frozen to allow for translation & documentation | Documentation Complete | Done | Only editing and and enhancing should take place after this point | Integration & System Test | Done | The system test for each user-facing feature must be complete and should run on Code Merge |
|
RC0 | 4/13/2017 | Name | Status |
---|
Bug fixes | Done | Release Candidate 0 | Done |
|
RC1 | 4/20/2017 | Name | Status |
---|
Bug fixes | Done | Release Candidate 1 | Done |
|
RC2 | 4/27/2017 | Name | Status |
---|
Bug fixes | Done | Release Candidate 2 | Done |
|
RC3 | 5/4//2017 | Name | Status | Description |
---|
Bugfix & more | Done | Bugfixing, performance improvement and other necessary / desired changes | Release Review | Done | Participating Projects must hold their Release Reviews, including User Facing Documentation | Release Candidate 3 | Done |
|
Formal Release | 5/11/2017 | Name | Status | Description |
---|
Formal Carbon Release |
| Release Patch |
| Release patch to the stable/carbon branch and bump versions |
|