Communicate code freeze to projects | Complete Sep 14, 2021 | 1 weeks before code freeze happens | @Daniel De La Rosa |
Code freeze (stable branch lock) | Complete Sep 20, 2021 | 1 weeks before any release. | @Anil Shashikumar Belur |
Pick RC and produce CSIT spreadsheet | Complete Sep 30, 2021 | All blocker bugs must be closed before picking the RC. This is tentative date. | @Daniel De La Rosa |
Vet CSIT failures | Complete Sep 30, 2021 | Max 1 week after CSIT spreadsheet is shared | all projects |
TSC votes the Managed release | Complete Sep 30, 2021 | TSC | |
Remind PTL to produce release notes (only for GA release) | Complete Sep 30, 2021 | Done automatically | |
Publish released artifacts to Nexus | CompleteOct 4, 2021 | @Anil Shashikumar Belur | |
Communicate Managed release to Self Managed projects | Complete Oct 4, 2021 | @Daniel De La Rosa | |
Unlock stable branch | CompleteOct 4, 2021 | @Anil Shashikumar Belur | |
Release All SM projects (including "official" distribution) | Complete Oct 13, 2021 | Max 1 week after Managed release. | All SM projects (including int/dist) |
Update docs | Complete Oct 15, 2021 |
| |
Branch docs project ( Only for GA release ) | CompleteOct 15, 2021 |
|