Release Checklist Template
Pending | Complete |
---|
Event / Timeline | Comments | Who | applies to SRs |
---|---|---|---|
Communicate code freeze to projects | 2 weeks before code freeze happens | release manager | yes |
Code freeze (stable branch lock) | 3 weeks before any release. | LF IT | yes |
Pick RC and produce CSIT spreadsheet | All blocker bugs must be closed before picking the RC. This is tentative date. | integration/test | yes |
Vet CSIT failures | Max 1 week after CSIT spreadsheet is shared. | all projects | yes |
TSC votes the Managed release | TSC | yes | |
Unlock stable branch | LF IT | yes | |
Remind PTL to produce release notes (only for GA release) | release manager | no | |
Publish released artifacts to Nexus | LF IT | yes | |
Communicate Managed release to Self Managed projects | release manager | yes | |
Release All SM projects (including "official" distribution) | Max 1 week after Managed release. | All SM projects (including int/dist) | yes |
Update docs |
| docs team | some |
Branch docs project |
| docs team | no |