Pending 22 Pending24 Pending 25 Pending 25 Pending 25 Pending 25 Pending  29 Mar Pending  29 Mar Pending 29 Mar
Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete  

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete  

1 weeks before any release.Anil Shashikumar Belur
Pick RC and produce CSIT spreadsheet

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Complete  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Complete  


TSC
Remind PTL to produce release notes (only for GA release)

Complete  

Done automaticallyrelease manager
Publish released artifacts to Nexus

Complete  


Communicate Managed release to Self Managed projects

Complete  


Unlock stable branch

Complete 


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Complete   

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Complete   


Branch docs project ( Only for GA release )

Complete  

  • on master branch bump versions to next release (conf.yaml)
    • Clear per-project release notes in master to prep for next release