Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Pending 05 Pending 
Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Done   

1 weeks before code freeze happens
Code freeze (stable branch lock)

Done   

1 weeks before any release.Anil Belu
Pick RC and produce CSIT spreadsheet

Done

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Done  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Approved  


TSC
Publish released artifacts to Nexus

In progress Done  


Communicate Managed release to Self Managed projects

Done  


Unlock stable branch

Done  


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Done  

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Done  


...