Pending | PendingComplete |
---|
Event / Timeline | Status | Comments | Who | |
---|---|---|---|---|
Communicate code freeze to projects | Complete | 1 weeks before code freeze happens | ||
Code freeze (stable branch lock) | PendingComplete | 1 weeks before any release. | Anil Shashikumar Belur | |
Pick RC and produce CSIT spreadsheet | Pending 20Complete | All blocker bugs must be closed before picking the RC. This is tentative date. | ||
Vet CSIT failures | Pending 22Complete | Max 1 week after CSIT spreadsheet is shared | all projects | |
TSC votes the Managed release | Pending 23Complete | TSC | ||
Remind PTL to produce release notes (only for GA release) | Pending 23Complete | Done automaticallyautomatically | release manager | |
Publish released artifacts to Nexus | Pending 24 SepComplete | |||
Communicate Managed release to Self Managed projects | Pending 24 SepComplete | |||
Unlock stable branch | Pending24 SepComplete | Anil Shashikumar Belur | ||
Release All SM projects (including "official" distribution) | Pending 30 SepComplete | Max 1 week after Managed release. | All SM projects (including int/dist) | |
Update docs | Pending 30 SepComplete |
| ||
Branch docs project ( Only for GA release ) | Pending 30 Sep Complete |
|
...