...
Event / Timeline | Status | Comments | Who | ||||
---|---|---|---|---|---|---|---|
Communicate code freeze to projects | Done | 1 weeks before code freeze happens | |||||
Code freeze (stable branch lock) | Done | 1 weeks before any release. | Anil Belu | ||||
Pick RC and produce CSIT spreadsheet | Done | All blocker bugs must be closed before picking the RC. This is tentative date. | |||||
Vet CSIT failures | Done | Max 1 week after CSIT spreadsheet is shared | all projects | ||||
TSC votes the Managed release | Approved | TSC | |||||
Publish released artifacts to Nexus | In progress Done | ||||||
Communicate Managed release to Self Managed projects | Pending 29Done | ||||||
Unlock stable branch | Pending 29Done | Anil Shashikumar Belur | |||||
Release All SM projects (including "official" distribution) | Pending 05Done | Max 1 week after Managed release. | All SM projects (including int/dist) | ||||
Update docs | PendingDone |
| Branch
| projectPending |
| py)docs team |