Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete  

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete 

1 weeks before any release.Anil Shashikumar Belur
Pick RC and produce CSIT spreadsheet

Complete  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Complete 

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Complete  


TSC
Publish released artifacts to Nexus

Complete 


Communicate Managed release to Self Managed projects

Complete  


Unlock stable branch

Complete 


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Complete  

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Complete   


...