...
Event / Timeline | Status | Comments | Who | |
---|---|---|---|---|
Communicate code freeze to projects | PendingComplete | 1 weeks before code freeze happens | ||
Code freeze (stable branch lock) | PendingObsolete | 1 weeks before any release. | Anil Shashikumar Belur | |
Pick RC and produce CSIT spreadsheet | Pending 16 AugRC | Complete | All blocker bugs must be closed before picking the RC. This is tentative date. | Daniel De La Rosa |
Vet CSIT failures | Pending 17 Aug Complete | Max 1 week after CSIT spreadsheet is shared | all projects | |
TSC votes the Managed release | Pending 18 Aug Complete | TSC | ||
Publish released artifacts to Nexus | PendingComplete Aug | |||
Communicate Managed release to Self Managed projects | Pending Complete Aug | |||
Unlock stable branch | PendingComplete Aug | Anil Shashikumar Belur | ||
Release All SM projects (including "official" distribution) | Pending 26 Aug Complete | Max 1 week after Managed release. | All SM projects (including int/dist) Luis Gomez Palacios | |
Update docs | Pending 26 Aug Complete |
|
...