...
Event / Timeline | Status | Comments | Who | |||
---|---|---|---|---|---|---|
Communicate code freeze to projects | PendingDone | 1 weeks before code freeze happens | ||||
Code freeze (stable branch lock) | Pending 27Done | 3 1 weeks before any release. | Anil Shashikumar Belur | |||
Pick RC and produce CSIT spreadsheet | PendingRC 266 has been picked.. CSIT spreadsheet DONE | All blocker bugs must be closed before picking the RC. This is tentative date. | ||||
Vet CSIT failures | PendingDONE | Max 1 week after CSIT spreadsheet is shared.shared | all projects | |||
TSC votes the Managed release | PendingAPPROVED | TSC | Unlock stable branch | Pending | Anil Shashikumar Belur | |
Remind PTL to produce release notes (only for GA release) | N/A | release manager | ||||
Publish released artifacts to Nexus | Pending 04Done | |||||
Communicate Managed release to Self Managed projects | Pending 04Done | |||||
Unlock stable branch | Done | Anil Shashikumar Belur | ||||
Release All SM projects (including "official" distribution) | Pending 11Done | Max 1 week after Managed release. | All SM projects (including int/dist) | |||
Update docs | Pending 11Done |
| Docs team | |||
Branch docs project | Pending ( Only for GA release ) | N/A |
| docs team |
...