...
Event / Timeline | Status | Comments | Who | |
---|---|---|---|---|
Communicate code freeze to projects | Complete | 1 weeks before code freeze happens | ||
Code freeze (stable branch lock) | Pending 13Complete | 1 weeks before any release. | Anil Shashikumar Belur | |
Pick RC and produce CSIT spreadsheet | Pending13Complete | All blocker bugs must be closed before picking the RC. This is tentative date. | ||
Vet CSIT failures | Pending16 NovComplete | Max 1 week after CSIT spreadsheet is shared | all projects | |
TSC votes the Managed release | Pending 19 NovComplete | TSC | ||
Publish released artifacts to Nexus | Pending 19 NovComplete | |||
Communicate Managed release to Self Managed projects | Pending 19 NovComplete | |||
Unlock stable branch | Pending 19 NovComplete | Anil Shashikumar Belur | ||
Release All SM projects (including "official" distribution) | Pending 27 NovComplete | Max 1 week after Managed release. | All SM projects (including int/dist) | |
Update docs | Pending27 NovComplete |
| Docs team |
...