Event / Timeline | Status | Comments | Who |
---|---|---|---|
Communicate code freeze to projects | Done | 1 weeks before code freeze happens | |
Code freeze (stable branch lock) |
Done | 1 weeks before any release. | Anil Belu |
Pick RC and produce CSIT spreadsheet |
Done |
All blocker bugs must be closed before picking the RC. This is tentative date. | ||
Vet CSIT failures |
Done | Max 1 week after CSIT spreadsheet is shared | all projects |
TSC votes the Managed release |
Approved | TSC | |
Publish released artifacts to Nexus |
Done | ||
Communicate Managed release to Self Managed projects |
Done | ||
Unlock stable branch |
Done | Anil Shashikumar Belur | |
Release All SM projects (including "official" distribution) |
Done | Max 1 week after Managed release. | All SM projects (including int/dist) |
Update docs |
Done |
|
Branch docs project
- Clear per-project release notes in master to prep for next release
|