...
Event / Timeline | Status | Comments | Who | |
---|---|---|---|---|
Communicate code freeze to projects | Done | 1 weeks before code freeze happens | ||
Code freeze (stable branch lock) | Done | 1 weeks before any release. | Anil Shashikumar Belur | |
Pick RC and produce CSIT spreadsheet | RC 266 has been picked.. CSIT spreadsheet DONE | All blocker bugs must be closed before picking the RC. This is tentative date. | ||
Vet CSIT failures | DONE | Max 1 week after CSIT spreadsheet is shared | all projects | |
TSC votes the Managed release | APPROVED | TSC | ||
Remind PTL to produce release notes (only for GA release) | N/A | release manager | ||
Publish released artifacts to Nexus | Done | |||
Communicate Managed release to Self Managed projects | Done | |||
Unlock stable branch | Done | Anil Shashikumar Belur | ||
Release All SM projects (including "official" distribution) | Done | Max 1 week after Managed release. | All SM projects (including int/dist) | |
Update docs | In progress 21Done |
| Docs team | |
Branch docs project | Pending ( Only for GA release ) | N/A |
| docs team |
...