Pending | PendingComplete |
---|
Event / Timeline | Status | Comments | Who |
---|---|---|---|
Communicate code freeze to projects | Complete | 1 weeks before code freeze happens | |
Code freeze (stable branch lock) | Complete | 1 weeks before any release. | Anil Shashikumar Belur |
Pick RC and produce CSIT spreadsheet | Complete | All blocker bugs must be closed before picking the RC. This is tentative date. | Daniel De La Rosa |
Vet CSIT failures | Complete | Max 1 week after CSIT spreadsheet is shared | all projects |
TSC votes the Managed release | Complete | TSC | |
Publish released artifacts to Nexus | Complete | ||
Communicate Managed release to Self Managed projects | Complete | ||
Unlock stable branch | Pending21Complete | Anil Shashikumar Belur | |
Release All SM projects (including "official" distribution) | Pending 24Complete | Max 1 week after Managed release. | All SM projects (including int/dist) Luis Gomez Palacios |
Update docs | Pending 28 FebComplete |
|
...