PendingComplete


Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete 

15 Feb

 

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete 

22 Feb

 

1 weeks before any release.Anil Shashikumar Belur
Pick RC and produce CSIT spreadsheet

Complete 

18 Mar

 

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Complete 

29 Mar

 

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Complete 

29 Mar

 


TSC
Remind PTL to produce release notes (only for GA release)

Complete 

29 Mar

 

Done
automatically
automatically 
release manager

Publish released artifacts to Nexus
Complete 30 Mar

Complete 


Communicate Managed release to Self Managed projects

Complete 

30 Mar

 


Unlock stable branch

Complete

30 Mar

 


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)
Complete  01 Apr

Complete  

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Complete  

14 Apr

 


Branch docs project ( Only for GA release )

Complete 06 Apr

Complete 

  • on master branch bump versions to next release (conf.yaml)
    • Clear per-project release notes in master to prep for next release
  • on new stable/branch update links to stable/branch away from "latest" (conf.py)