Pending | Complete |
---|
Event / Timeline | Status | Comments | Who |
---|---|---|---|
Communicate code freeze to projects | Complete |
| 1 weeks before code freeze happens | |
Code freeze (stable branch lock) | Complete |
| 1 weeks before any release. | Anil Shashikumar Belur |
Pick RC and produce CSIT spreadsheet | Complete |
| All blocker bugs must be closed before picking the RC. This is tentative date. | |
Vet CSIT failures | Complete |
| Max 1 week after CSIT spreadsheet is shared | all projects |
TSC votes the Managed release | Complete |
| TSC | |
Remind PTL to produce release notes (only for GA release) | Complete |
| Done |
automatically |
Publish released artifacts to Nexus |
Complete | ||
Communicate Managed release to Self Managed projects | Complete |
| ||
Unlock stable branch | Complete |
| Anil Shashikumar Belur | |
Release All SM projects (including "official" distribution) |
Complete | Max 1 week after Managed release. | All SM projects (including int/dist) |
Update docs | Complete |
|
| |
Branch docs project ( Only for GA release ) |
Complete |
|