Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Done  18 May Done  

1 weeks before code freeze happens
Code freeze (stable branch lock)

Done  25 May Done  

1 weeks before any release.Anil BeluShashikumar Belur
Pick RC and produce CSIT spreadsheet

Done 26 May Done 

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Done 27 May  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Approved 28 May Done  


TSC
Publish released artifacts to Nexus

In progress 31 Done  


Communicate Managed release to Self Managed projects

Done 28 May  


Unlock stable branch

Done 28 May  


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Done 03 Jun  

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Done 05 Jun  


...