Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Complete  

1 weeks before code freeze happens
Code freeze (stable branch lock)

Complete 

1 weeks before any release.Anil Shashikumar Belur
Pick RC and produce CSIT spreadsheet

Pending 08  

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Pending 08  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Pending 15  


TSCRemind PTL to produce release notes (only for GA release)

Pending  

Done automatically 
Publish released artifacts to Nexus

Pending 


Communicate Managed release to Self Managed projects

Pending  


Unlock stable branch

Pending 


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Pending   

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Pending   


...