Event / Timeline | Status | Comments | Who |
---|---|---|---|
Communicate code freeze to projects | Complete | 1 weeks before code freeze happens | |
Code freeze (stable branch lock) | Pending 26 | 1 weeks before any release. | Anil Shashikumar Belur |
Pick RC and produce CSIT spreadsheet | Pending 26 | All blocker bugs must be closed before picking the RC. This is tentative date. | |
Vet CSIT failures | Pending 26 | Max 1 week after CSIT spreadsheet is shared | all projects |
TSC votes the Managed release | Pending | TSC | |
Publish released artifacts to Nexus | Pending | ||
Communicate Managed release to Self Managed projects | Pending | ||
Unlock stable branch | Pending | Anil Shashikumar Belur | |
Release All SM projects (including "official" distribution) | Pending | Max 1 week after Managed release. | All SM projects (including int/dist) |
Update docs | Pending |
|
...