Done  18 May Done  25 May Done 26 May Done 27 May Approved 28 May In progress 31 Done 28 May Done 28 May Done 03 Jun Done 05 Jun
Event / TimelineStatusCommentsWho
Communicate code freeze to projects

Pending  

1 weeks before code freeze happens
Code freeze (stable branch lock)

Pending  

1 weeks before any release.Anil Belu
Pick RC and produce CSIT spreadsheet

Pending 

All blocker bugs must be closed before picking the RC. This is tentative date.
Vet CSIT failures

Pending  

Max 1 week after CSIT spreadsheet is shared all projects
TSC votes the Managed release

Pending  


TSC
Publish released artifacts to Nexus

Pending  


Communicate Managed release to Self Managed projects

Pending  


Unlock stable branch

Pending  


Anil Shashikumar Belur
Release All SM projects (including "official" distribution)

Pending  

Max 1 week after Managed release.All SM projects (including int/dist)
Update docs

Pending  


...