| Event / Timeline | Status | Comments | Who |
|---|---|---|---|
| Communicate code freeze to projects | Complete | 1 weeks before code freeze happens | |
| Code freeze (stable branch lock) | Complete | 1 weeks before any release. | Anil Shashikumar Belur |
| Pick RC and produce CSIT spreadsheet | Complete | All blocker bugs must be closed before picking the RC. This is tentative date. | Daniel De La Rosa |
| Vet CSIT failures | Complete | Max 1 week after CSIT spreadsheet is shared | all projects |
| TSC votes the Managed release | PendingComplete | TSC | |
| Publish released artifacts to Nexus | PendingComplete | ||
| Communicate Managed release to Self Managed projects | PendingComplete | ||
| Unlock stable branch | PendingComplete | Anil Shashikumar Belur | |
| Release All SM projects (including "official" distribution) | PendingComplete | Max 1 week after Managed release. | All SM projects (including int/dist) Luis Gomez Palacios |
| Update docs | PendingComplete |
|
...