| Event / Timeline | Status | Comments | Who |
|---|---|---|---|
| Communicate code freeze to projects | Done | 1 weeks before code freeze happens | |
| Code freeze (stable branch lock) | Done | 1 weeks before any release. | Anil Belu |
| Pick RC and produce CSIT spreadsheet | Done | All blocker bugs must be closed before picking the RC. This is tentative date. | |
| Vet CSIT failures | Done | Max 1 week after CSIT spreadsheet is shared | all projects |
| TSC votes the Managed release | Approved | TSC | |
| Publish released artifacts to Nexus | In progress Done | ||
| Communicate Managed release to Self Managed projects | Done | ||
| Unlock stable branch | Done | Anil Shashikumar Belur | |
| Release All SM projects (including "official" distribution) | Done | Max 1 week after Managed release. | All SM projects (including int/dist) |
| Update docs | Done |
|
...